At EICON Building Group, our primary goal is to make the process of building your new home enjoyable and easy to understand experience. Knowing what stage your home is at is crucial for you to prepare for your move, but also pick out your selections.

In this section, you will find an outline of the step-by-step guide in our building process and approximately, how long you can expect those steps to take.

Please keep in mind that we look at every home individually and every project is unique, and therefore the time estimate can vary based on the size of home as well as other factors such as weather.

EICON Building Group takes our job of managing the building process seriously and we are also aware that our ability to ensure a successful and stress-free homebuilding experience for our customers is directly related to the amount of customer referrals and repeat business we experience. That is the lifeblood of our business and we work tirelessly to earn it.

Please review the steps and stages below and contact us if you have any questions!

• Planning (30-180 days)
Lot selection, architectural planning, engineering and developer’s approvals, acquiring permits, scheduling

• Site Work (5-7 days)
Lot staked, trees and brush removed, excavation, excess dirt removal if necessary

• Foundation (14-17 days)
Footings framed and poured, foundation walls framed and poured, waterproofing of foundation, foundation back-filled

• Framing (30-35 days)
Rough framing of exterior shell, interior walls framed, exterior trim and windows installed, exterior siding and/or masonry walls installed, framing inspection completed, roof shingled

• Rough-in Plumbing

• Rough-in Electrical

• Mechanical (30-35 days)

• Pre-Finish (14-17 days)
Sealing exterior penetrations, insulation installed in walls and vaults, vents covered, sound insulation installed if required, sheetrock hung and finished, ceilings textured if needed, floors scraped and home scrapped out, walls and ceilings primed and inspected

• Finish (30-35 days)
Cabinets installed, trim constructed, hardwood floors laid, tile and stone installed, paint interior and exterior, hardwood floors sanded and first coat completed, pre-carpet cleaning completed

• Final Finish (30 days)
Plumbing fixtures installed, electric finished and lighting fixtures hung, HVAC system completed, audio system completed, hardwood floors second and third coats completed, wall covering and appliances installed, door and cabinet hardware installed, carpeting completed, windows scraped and cleaned, entire home cleaned, paint touch-up

• Completion (20 days)
Yard final graded, irrigation system installed if purchased, landscaping installed, final inspections and repairs made, home orientation scheduled, closing, MOVE IN!

• 90 Day Customer Service (90 days after closing)
Minor repairs as needed, change and/or clean furnace filters

• 360 Day Customer Service (1 year after closing)
Minor repairs as needed, change and/or clean furnace filters. Tell your friends how much you love your new EICON home!

• 10 Years Later… Call EICON Building Group to start planning your next dream home!

***Please note these are ideal timelines and are subject to conditions that vary during construction season.